Vernon Google 001 — 850 MW under construction
Vernon Google 001 is a hyperscale data centre operated by Google in Vernon, United States, in the Vernon (Wilbarger County) market.
- Who operates Vernon Google 001?
- Google.
- Where is Vernon Google 001?
- Vernon, United States, in the Vernon (Wilbarger County) market.
- What is the capacity of Vernon Google 001?
- 850 MW under construction.
Project tracker
850 MW under construction
Construction figure, from one source and not yet corroborated.
850 MW under construction in the Vernon (Wilbarger County) market, which has 850 MW of total potential at full buildout and none of it live yet.
The market today · Vernon (Wilbarger County)
- Under construction
- 850 MW
- Total potential
- 850 MW
Timeline
Vernon Google 001 — announced
We’re expanding our longstanding presence in Texas with a new data center under construction in Wilbarger County and agreements to support local energy resilience, anchored by a focus on water security and energy affordability.
Source: blog.google
Vernon Google 001 — broke ground
Project Rise 1A is located at FM 2897 S in Vernon and saw work begin on March 31, 2026.
Source: datacenterdynamics.com
Also announced or under construction by Google
Coordinates
Position
34.15, -99.27
Location precision
Approximate
Beyond the location
DC Atlas tracks the grid connection behind data centres across 65 countries — who supplies the power, the market it sits in, and what is being built next.
Sign up free