Geneva / Lausanne: 10 data centres, 6 operators, 56 MW live

Geneva / Lausanne, Switzerland holds 10 data centres, spanning 5 sub-markets, 6 operators, 56 MW live (18% modelled). STACK Infrastructure alone accounts for 2 sites, ahead of Swisscom.

Map of 9 data centres in Geneva / Lausanne

Every Geneva / Lausanne site DC Atlas tracks with a position on record, coloured by status.

Open Geneva / Lausanne in the ExplorerFilter, compare and search every facility on the live map. Free account, no card.

Geneva / Lausanne is one scope of the whole corpus. See every facility DC Atlas tracks on the global data center map.

Embed the Geneva / Lausanne data center map

Paste this into any page. The map stays live as the data changes, every pin still opens its facility page, and the frame carries a link back to DC Atlas. Free to use, no key needed.

Customise this embedPick a country, market or operator, narrow it by status and type, set the size, and watch the map update as you choose.Open the embed builder

Live

56MW

18% modelled

Under construction

0MW

Planned

0MW

Total potential

61MW

Who is building in Geneva / Lausanne

The 6 largest operators here by total potential, of 6 tracked in this market.

OperatorSitesLiveTotal potential
STACK Infrastructure234 MW34 MW
Swisscom210 MW10 MW
euNetworks10.2 MW5 MW
nLighten14.2 MW4.2 MW
CERN14 MW4 MW
Equinix23.4 MW3.4 MW

Only 30% of the live facilities here carry a commissioning date across too few years, which is too thin to chart as a build history.

Recent activity

6 recorded developments in the Geneva / Lausanne market, the latest on 16 Dec 2025.

  • 16 Dec 2025Permit filed

    STACK Infrastructure files work-time permit for Swiss data center

    STACK Infrastructure Switzerland SA filed a request for a work-time permit with the Swiss State Secretariat for Economic Affairs (SECO) on December 16, 2025, for operation and maintenance of its Group I data center facility in Gland, Vaud. The permit application covers technical building operations and maintenance activities. The permit is valid from January 12, 2026 to January 12, 2029. This indicates active data center operations at the Gland location.

  • 14 Nov 2024Permit filed

    Equinix Switzerland Files Work-Time Permit for Geneva Data Center Operations

    Equinix (Switzerland) Sàrl filed a request for a work-time permit with the Swiss State Secretariat for Economic Affairs (SECO) for its Vernier facility in Geneva. The permit covers technical facility management and emergency maintenance interventions at Equinix's client data centers in Geneva. The permit was filed on 2024-09-08 and is valid through 2027-09-07, classified as a renewal of existing authorization.

  • 1 Nov 2023Acquisition

    Vernier Lumen 001 ownership change

    Vernier Lumen 001 changed ownership on 1 November 2023, when Lumen Technologies closed the sale of its EMEA business to Colt Technology Services.

  • 22 May 2023Announced

    LUKOIL Technology Services Registers Geneva Data Center Branch

    LUKOIL Technology Services GmbH, an Austrian limited liability company based in Vienna, registered a new branch office in Geneva, Switzerland on May 22, 2023. The branch, located at Rue Kazem-Radjavi 3, is authorized to provide IT support services and operate a data center (centre de traitement des données). The registration was published in the Swiss official commercial gazette (SHAB) and assigned the registration number CHE-219.670.155. This marks LUKOIL's formal establishment of data center operations in the Geneva canton.

  • 2 Nov 2022Announced

    Vernier Lumen 001 announced

    The divestiture covering Vernier Lumen 001 was announced on 2 November 2022, under which Lumen agreed to sell its EMEA business, including its terrestrial and subsea networks, data centers and network equipment, to London-headquartered Colt.

  • 14 Sept 2007Acquisition

    Geneva Equinix 005 — changed ownership

    including centers in Dusseldorf, Frankfurt, Geneva, London, Munich, Paris and Zurich

All recent activity

Questions about Geneva / Lausanne

How many data centres are in Geneva / Lausanne?
Geneva / Lausanne, Switzerland holds 10 data centres, spanning 5 sub-markets, 6 operators, 56 MW live (18% modelled). STACK Infrastructure alone accounts for 2 sites, ahead of Swisscom.
How much data centre capacity does Geneva / Lausanne have?
DC Atlas tracks 10 data centres in the Geneva / Lausanne data centre market. 56 MW is live, for 61 MW of total potential at full buildout.
Who are the largest data centre operators in Geneva / Lausanne?
6 operators run facilities in the Geneva / Lausanne data centre market. STACK Infrastructure is the largest by total potential, with 2 sites and 34 MW.

Every data centre we track in Geneva / Lausanne

9 of 10 with a published page

Other markets in Switzerland